Who's Online
There currently are 5940 guests and 6 members online.
|
Categories
|
Information
|
Featured Product
|
|
|
|
|
There are currently no product reviews.
;
Excellent service manual includes everything is need to repair this radio-caseete, how to disassemble, wiring diagram, all , waiting time until the download was only a few hours. I'm going to buy service manuals from here, are cheap and very good.Thank you.
;
Good service manual,i saved from scrapping this deck,is now fully functional.Thanks.
;
Found this to be the manual included with the original packinging, was helpfull but did not give any detailed repair instructions.
;
Complete service manual, was very helpful in repairing this tapedeck.Thanks.
;
The service manual was a copy of the original from Wirlpool. The quality was good, all neccecary information was available including the service-codenumbers, so I could order the right part to be replaced for repair.
Downloding was no probem after the payment.
Thanks for the service!
Left side gears
To remove the left side gears
1 2 3 4 5 6 7 8 9 Remove the top cover. Remove the left side cover. Remove the fusing assembly. Remove the screw shown in callout 1, Figure 6-47 on page 185 and remove the black plastic piece. Disconnect all connectors from the paper feed PCB and free the cables from the cable stays. Remove the screw securing the gear cover and remove the cover shown in callout 3, Figure 6-47 on page 185. Remove the fuser motor. Remove the paper path motor. Remove the three clutches: CL2, CL3, and CL4.
10 Remove the four screws (callout 1, Figure 6-55 on page 194) and remove the sheet metal over the gears. 11 Remove the one or two screws (shown in callout 2, Figure 6-55 on page 194) and e-clip (shown in callout 3, Figure 6-55 on page 194) that hold the solenoid assembly in place and then remove the solenoid assembly. 12 Remove any e-clips or bushings necessary to remove the affected gears.
Left side gear replacement
1 2 3 Install the back half of the large double gear shown in callout 1, Figure 6-56 with the small portion of the gear (18T) facing outward. Install the two gears (shown in callout 2, Figure 6-56 on page 194) so they cover the back half of the large double gear. Install the remaining gears and the front half of the large double gear so they appear as shown in Figure 6-56 on page 194.
CAUTION
When reinstalling the solenoid assembly, make sure that the flat parts of the pickup rollers are down and that the plastic spring-loaded gear is fully engaged.
C7085-90921
Chapter 6 Removal and replacement 193
|
|
|
> |
|